UNIVERSITY OF ECONOMICS HO CHI MINH CITY
International School of Business
------------------------------
NGUYEN ANH KHOA
INEFFECTIVE PROJECT
SCHEDULING AND TIME CONTROL
IN SUN VIET JSC
MASTER OF BUSINESS ADMINISTRATION
Ho Chi Minh City – Year 2018
LUAN VAN CHAT LUONG download : add [email protected]
Page 2 of 56
UNIVERSITY OF ECONOMICS HO CHI MINH CITY
International School of Business
------------------------------
NGUYEN ANH KHOA
INEFFECTIVE PROJECT
SCHEDULING AND TIME CONTROL
IN SUN VIET JSC
MASTER OF BUSINESS ADMINISTRATION
SUPERVISOR: Dr. NGUYEN PHONG NGUYEN
Ho Chi Minh City – Year 2018
LUAN VAN CHAT LUONG download : add [email protected]
Page 3 of 56
CONTENTS
1. Problem identification ..............................................................................................6
1.1. Company background........................................................................................6
1.2. Symptom and evidence......................................................................................7
1.3. Qualitative research ...........................................................................................9
1.4. Initial causes-effect map..................................................................................10
1.5. Updated causes-effect map..............................................................................14
1.6. Potential central problem.................................................................................17
2. Problem justification ..............................................................................................19
2.1. Problem definition ...........................................................................................19
2.2. Problem existence............................................................................................21
2.3. Problem consequences.....................................................................................22
3. Causes validation....................................................................................................24
3.1. List of real causes............................................................................................24
3.2. Final causes-effect map ...................................................................................27
3.3. Causes evaluation ............................................................................................28
4. Alternative solution ................................................................................................29
5. Action plan .............................................................................................................33
6. Supporting information ..........................................................................................37
6.1. Interview guide (first interview)......................................................................37
6.2. Summary of finding from qualitative research (first interview) .....................38
6.3. Group of causes and variable base on result of interview (first interview).....47
6.4. Analysis the number of time overrun projects in 2017 by factors ..................48
6.5. Result of SVTECH’s control system measurement ........................................48
6.6. Transcript of problem discussion (third interview).........................................50
6.7. Result of causes evaluation .............................................................................53
REFERENCES............................................................................................................55
LUAN VAN CHAT LUONG download : add [email protected]
Page 4 of 56
List of figures
Figure 1. Initial Causes-effect map (source: in-depth interview) .................................10
Figure 2. Updated causes-effect map (source: in-depth interview and the above
literatures) .....................................................................................................................14
Figure 3. Finial causes-effect map (source: in-depth interview and the above literatures)
.......................................................................................................................................27
List of table
Table 1. KPI of Company in 2017 (source: SVTECH’s data)........................................7
Table 2. Relationship between factors and variables in causes-effect maps (interview
and above literatures)....................................................................................................15
Table 3. Result of adding interview (source: second interview) .................................16
Table 4. Y (time) of project in 2017 (source: SVTECH’s data)...................................21
Table 5. Y (time) in three year 2015-2017 (source: SVTECH’s data).........................22
Table 6. Percentage of over time cost to revenue in 2015-2017 (source: SVTECH’s data)
.......................................................................................................................................24
Table 7. Group of causes (source: literature review)....................................................25
Table 8. Summarizing of causes evaluation..................................................................28
Table 9. Summary of finding in first in-depth interview (source: first in-depth interview)
.......................................................................................................................................39
Table 10. Group of causes and variable (source: first in-depth interview)...................47
Table 11. Number of time overrun project summarized by main factors (source:
SVTECH’s data) ...........................................................................................................48
Table 12. Time in plan and actual time to finish project in 2017 (source: SVTECH’s
data)...............................................................................................................................48
LUAN VAN CHAT LUONG download : add [email protected]
Page 5 of 56
EXECUTIVE SUMMARY
SVTECH had problem in deploying project in 2017. The proportion of time overrun
projects and number of delayed day rose significantly. They leaded to complaints from
customers, probability to face with liquidated damages penalty and increase cost
because of overtime cost. More seriously, SVTECH could be lost customers for
competitors if the time overrun project do not be solved. By making interview, literature
review and analyzing the data in 2017, ineffective time control system was found that
the central problem caused to the time overrun project. In order to solve this problem,
deeper interview and study research was done. The result of research and interview
defined 7 causes of ineffective time control system, which are classified in 3 groups.
These causes has been validated and evaluated to define the level of important to
company. Based on these causes, alternative solution has been suggested and discussed
to find the suitable one for SVTECH. To make clear for the solution, an action plan was
made. This action plan is expected to help SVTECH improve the time control system
and decrease the percentage of time overrun projects and number of delayed day.