Thư viện tri thức trực tuyến
Kho tài liệu với 50,000+ tài liệu học thuật
© 2023 Siêu thị PDF - Kho tài liệu học thuật hàng đầu Việt Nam

Electrical Power Systems Quality, Second Edition phần 9 potx
Nội dung xem thử
Mô tả chi tiết
capability to electromechanical network relays. In the past, these supplemental relays had minimum time delays of 1 s or more since their
mission was to wait for the elevator to descend. However, not all utilities endorse this low-current, time-delay technique. Some feel that
any time delay in opening the network protectors degrades the high
service quality that the network system is intended to provide.
The load-generation control and DG tripping schemes mentioned
above are intended to ensure that the network protectors are never
opened by exported power. As long as the schemes work properly, the
network protectors are never exposed to the out-of-phase voltage conditions that may exceed the switch capability. However, because of the
potentially catastrophic consequences of causing a network protector
failure, it is prudent to provide a backup. An interlocking scheme that
trips the DG instantaneously when a certain number of network protectors have opened ensures that the network protectors will not be
exposed to out-of-phase voltages for more than a few cycles. The decision as to how many protectors must open before the DG is tripped
(one, two, or all) is a tradeoff between security of the protectors and
nuisance tripping of the DG. Note that this scheme does not relieve the
DG installer from the responsibility of providing stuck-breaker backup
protection for the DG’s switching device.
An even more secure approach to avoiding overstressing the network
protectors is to replace existing protectors with new designs that are
capable of interrupting fault currents from sources with higher X/R
422 Chapter Nine
Time
Adjustable
delay time
Time delay for
low currents
Adjustable
instantaneous trip
threshold Instantaneous trip
for higher currents
100
Current (% of transformer rating)
Figure 9.32 Adjustable reverse-power characteristic.
Distributed Generation and Power Quality
Downloaded from Digital Engineering Library @ McGraw-Hill (www.digitalengineeringlibrary.com)
Copyright © 2004 The McGraw-Hill Companies. All rights reserved.
Any use is subject to the Terms of Use as given at the website.
ratios and of withstanding out-of-phase voltages across the open
switch. One major U.S. manufacturer of network protector units has
recently introduced such high-capacity protectors in 800- to 2250-A ratings and plans to introduce them in ratings up to 6000 A. These protectors are designed to be retrofitted in many existing types of network
units.
A possible DG interconnection problem exists that would involve network protectors without a network bus interconnection. If a DG is
interconnected on a feeder that also supplies a network unit, then if its
feeder breaker is tripped and the DG is not rapidly isolated, it may
impact one or more of the network units as if it were isolated on the network bus. For this type of event to occur, the DG output does not have
to be matched to the feeder load. For the excess generation case, it only
has to be momentarily greater than the load on the network bus. Under
this condition the power continues to flow to the network bus from the
feeder with the interconnected DG, which keeps that protector closed.
However, the excess power flows through the network back to the other
feeders, resulting in the opening of the protectors connected to those
feeders. Once open, these protectors will be separating two independent systems. For the case of less generation than load, the protector
connecting to the feeder with the generation may trip. Again, such a
condition would have a protector separating two independent systems.
Therefore, such DG applications should be avoided unless the DG
breaker is interlocked with the feeder breaker with a direct transfer
trip scheme.
9.7 Siting DG
The value of DG to the power delivery system is very much dependent
on time and location. It must be available when needed and must be
where it is needed. This is an often neglected or misunderstood concept
in discussions about DG. Many publications on DG assume that if 1
MW of DG is added to the system, 1 MW of additional load can be
served. This is not always true.
Utility distribution engineers generally feel more comfortable with
DG installed on facilities they maintain and control. The obvious choice
for a location is a substation where there is sufficient space and communications to control centers. This is an appropriate location if the
needs are capacity relief on the transmission system or the substation
transformer. It is also adequate for basic power supply issues, and one
will find many peaking units in substations. However, to provide support for distribution feeders, the DG must be sited out on the feeder
away from the substation. Such generation will also relieve capacity
constraints on transmission and power supply. In fact, it is more effecDistributed Generation and Power Quality 423
Distributed Generation and Power Quality
Downloaded from Digital Engineering Library @ McGraw-Hill (www.digitalengineeringlibrary.com)
Copyright © 2004 The McGraw-Hill Companies. All rights reserved.
Any use is subject to the Terms of Use as given at the website.
tive than the same amount of DG installed in the substation.
Unfortunately, this generation is usually customer-owned and distribution planners are reluctant to rely on it for capacity.
The application of DG to relieve feeder capacity constraints is illustrated in Fig. 9.33. The feeder load has grown to where it exceeds a
limit on the feeder. This limit could be imposed by either current ratings on lines or switchgear. It could also be imposed by bus voltage limits. There is DG on the feeder at a location where it can actually relieve
the constraint and is dispatched near the daily peak to help serve the
load. The straightforward message of the figure is that the load that
would otherwise have to be curtailed can now be served. Therefore, the
reliability has been improved.
This application is becoming more common as a means to defer
expansion of the wire-based power delivery infrastructure. The generation might be leased for a peak load period. However, it is more common to offer capacity credits to customers located in appropriate areas
to use their backup generation for the benefit of the utility system. If
there are no customers with DG in the area, utilities may lease space
to connect generation or, depending on regulatory rules, may provide
some incentives for customers to add backup generation.
There is by no means universal agreement that this is a permanent
solution to the reliability problem. When utility planners are shown
Fig. 9.33, most will concede the obvious, but not necessarily agree that
this situation represents an improvement in reliability. Three of the
stronger arguments are
1. If the feeder goes out, only the customer with the DG sees an
improvement in reliability. There is no noticeable change in the service reliability indices.
424 Chapter Nine
Feeder Limit DG Dispatched
ON
Daily Load Profile
DG Sited to Provide Feeder Relief
Figure 9.33 DG sited to relieve feeder overload constraint.
Distributed Generation and Power Quality
Downloaded from Digital Engineering Library @ McGraw-Hill (www.digitalengineeringlibrary.com)
Copyright © 2004 The McGraw-Hill Companies. All rights reserved.
Any use is subject to the Terms of Use as given at the website.
2. Customer generation cannot be relied upon to start when needed.
Thus, the reliability cannot be expected to improve.
3. Using customer-owned generation in this fashion masks the true
load growth. Investment in wire facilities lags behind demand,
increasing the risk that the distribution system will eventually not
be able to serve the load.
It should also be noted that the capacity relief benefit is nullified
when the distribution system is upgraded and no longer has a constraint. Thus, capacity credits offered for this application generally
have a short term ranging from 6 months to 1 year.
If one had to choose a location on the distribution feeder, where
should the DG be located? The optimal DG siting problem is similar to
the optimal siting problem for shunt capacitor banks. Many of the same
algorithms can be used with the chief difference being that the object
being added produces watts in addition to vars. Some of the same rules
of thumb also apply. For example, if the load is uniformly distributed
along the feeder, the optimal point for loss reduction and capacity relief
is approximately two-thirds of the way down the main feeder. When
there are more generators to consider, the problem requires computer
programs for analysis.
The utility does not generally have a choice in the location of feederconnected DG. The location is given for customer-owned generation,
and the problem is to determine if the location has any capacity-related
value to the power delivery system. Optimal siting algorithms can be
employed to evaluate the relative value of alternative sites.
One measure of the value of DG in a location is the additional
amount of load that can be served relative to the size of the DG.
Transmission networks are very complex systems that are sometimes
constrained by one small area that affects a large geographical area. A
relatively small amount of load reduction in the constrained area
allows several times that amount of load to be served by the system.
This effect can also be seen on distribution feeders. Because of the
simple, radial structure of most feeders, there is generally not a constraint so severe that DG application will allow the serving of additional load several times greater than the size of the generator.
However, there can be a multiplying effect as illustrated in Fig. 9.34.
This example assumes that the constraint is on the feeder rather
than on the substation. If 1 MW of generation were placed in the substation, no additional load could be served on the feeder because no
feeder relief has been achieved. However, if there is a good site on the
feeder, the total feeder load often can grow by as much as 1.4 MW. This
is a typical maximum value for this measure of DG benefit on radial
distribution feeders.
Distributed Generation and Power Quality 425
Distributed Generation and Power Quality
Downloaded from Digital Engineering Library @ McGraw-Hill (www.digitalengineeringlibrary.com)
Copyright © 2004 The McGraw-Hill Companies. All rights reserved.
Any use is subject to the Terms of Use as given at the website.
Another application that is becoming common is the use of DG to
cover contingencies. Traditionally, utilities have built sufficient wirebased delivery capacity to serve the peak load assuming one major failure (the so-called N-1 contingency design criterion). At the distribution
feeder level, this involves adding sufficient ties to other feeders so that
the load can be conveniently switched to an alternate feeder when a
failure occurs. There must also be sufficient substation capacity to
serve the normal load and the additional load expected to be switched
over during a failure. This results in substantial overcapacity when the
system is in its normal state with no failures.
One potentially good economic application of DG is to provide support for feeders when it is necessary to switch them to an alternate
source while repairs are made. Figure 9.35 depicts the use of DG
located on the feeder for this purpose. This will be substantially less
costly than building a new feeder or upgrading a substation to cover
this contingency.
The DG in this case is located near the tie-point between two feeders.
It is not necessarily used for feeder support during normal conditions
although there would often be some benefits to be gained by operating
the DG at peak load. When a failure occurs on either side of the tie, the
open tie switch is closed to pick up load from the opposite side. The DG
is dispatched on and connected to help support the backup feeder.
Locating the DG in this manner gives the utility additional flexibility and more reconfiguration options. Currently, the most common DG
technology used for this application is currently diesel gensets. The
gensets may be mounted on portable trailers and leased only for the
peak load season when a particular contingency leaves the system vulnerable. One or more units may be interconnected through a pad426 Chapter Nine
Pload
Pgen
= 0
Pload
Pgen
= 1.4
Figure 9.34 Ability of DG to increase the capacity of a distribution feeder is
dependent on DG location.
Distributed Generation and Power Quality
Downloaded from Digital Engineering Library @ McGraw-Hill (www.digitalengineeringlibrary.com)
Copyright © 2004 The McGraw-Hill Companies. All rights reserved.
Any use is subject to the Terms of Use as given at the website.