Thư viện tri thức trực tuyến
Kho tài liệu với 50,000+ tài liệu học thuật
© 2023 Siêu thị PDF - Kho tài liệu học thuật hàng đầu Việt Nam

Electrical Power Systems Quality, Second Edition phần 4 docx
Nội dung xem thử
Mô tả chi tiết
charge voltage may be reduced only a few percent, the greatest benefit
of the scout scheme may be that it greatly reduces the rate of rise of
surge voltages entering the cable. These steep-fronted surges reflect off
the open point and frequently cause failures at the first or second padmount transformer from the end. Because of lead lengths, arresters are
not always effective against such steep impulses. The scout scheme
practically eliminates these from the cable.
Many distribution feeders in densely populated areas will have scout
schemes by default. There are sufficient numbers of transformers that
there are already arresters on either side of the riser pole.
4.6 Managing Ferroresonance
Ferroresonance in a distribution system occurs mainly when a lightly
loaded, three-phase transformer becomes isolated on a cable with one
or two open phases. This can happen both accidentally and intentionally. Strategies for dealing with ferroresonance include
■ Preventing the open-phase condition
■ Damping the resonance with load
■ Limiting the overvoltages
■ Limiting cable lengths
■ Alternative cable-switching procedures
Most ferroresonance is a result of blown fuses in one or two of the
phases in response to faults, or some type of single-pole switching in
the primary circuit. A logical effective measure to guard against ferroresonance would be to use three-phase switching devices. For example, a three-phase recloser or sectionalizer could be used at the riser
pole instead of fused cutouts. The main drawback is cost. Utilities could
not afford to do this at every riser pole, but this could be done in special cases where there are particularly sensitive end users and frequent
fuse blowings.
Another strategy on troublesome cable drops is to simply replace the
fused cutouts with solid blades. This forces the upline recloser or
breaker to operate to clear faults on the cable. Of course, this subjects
many other utility customers to sustained interruptions when they
would have normally seen only a brief voltage sag. However, it is an
inexpensive way to handle the problem until a more permanent solution is implemented.
Manual, single-phase cable switching by pulling cutouts or cable
elbows is also a major source of ferroresonance. This is a particular
problem during new construction when there is a lot of activity and the
Transient Overvoltages 157
Transient Overvoltages
Downloaded from Digital Engineering Library @ McGraw-Hill (www.digitalengineeringlibrary.com)
Copyright © 2004 The McGraw-Hill Companies. All rights reserved.
Any use is subject to the Terms of Use as given at the website.
transformers are not yet loaded. Some utilities have reported that line
crews carry a “light board” or some other type of resistive load bank in
their trucks for use in cable-switching activity when the transformers
have no other load attached. One must be particularly careful when
switching delta-connected transformers; such transformers should be
protected because voltages may get extremely high. The common
grounded wye-wye pad-mounted transformer may not be damaged
internally if the exposure time is brief, although it may make considerable noise. When switching manually, the goal should be to open or
close all three phases as promptly as possible.
Ferroresonance can generally be damped out by a relatively small
amount of resistive load, although there are exceptions. For the typical case with one phase open, a resistive load of 1 to 4 percent of the
transformer capacity can greatly reduce the effects of ferroresonance. The amount of load required is dependent on the length of
cable and the design of the transformers. Also, the two-phase open
case is sometimes more difficult to dampen with load. Figure 4.38
shows the effect of loading on ferroresonance overvoltages for a
transformer connected to approximately 1.0 mi (1.61 km) of cable
with one phase open. This was a particularly difficult case that damaged end-user equipment. Note the different characteristics of the
phases. The transformer was of a five-legged core design, and the
middle phase presents a condition that is more difficult to control
158 Chapter Four
0 5 10 15 20 25 30
1
1.2
1.4
1.6
1.8
2
2.2
2.4
2.6
2.8
3
A
B
C
Ferroresonant Voltage (per Unit)
Resistive Load @ 480 V BUS (% Transformer Capacity)
Figure 4.38 Example illustrating the impact of loading on ferroresonance.
Transient Overvoltages
Downloaded from Digital Engineering Library @ McGraw-Hill (www.digitalengineeringlibrary.com)
Copyright © 2004 The McGraw-Hill Companies. All rights reserved.
Any use is subject to the Terms of Use as given at the website.
with loading. Five percent resistive load reduces the overvoltage
from approximately 2.8 to 2 pu. The transformer would have to be
loaded approximately 20 to 25 percent of resistive equivalent load to
limit ferroresonance overvoltages to 125 percent, the commonly
accepted threshold. Since such a large load is required, a three-phase
recloser was used to switch the cable.
On many utility systems, arresters are not applied on every padmounted distribution transformer due to costs. However, surge
arresters can be an effective tool for suppressing the effects of ferroresonance. This is particularly true for transformers with ungrounded primary connections where the voltages can easily reach 3 to 4 pu if
unchecked. Primary arresters will generally limit the voltages to 1.7 to
2.0 pu. There is some risk that arresters will fail if subjected to ferroresonance voltages for a long time. In fact, secondary arresters with
protective levels lower than the primary-side arresters are frequent
casualties of ferroresonance. Utility arresters are more robust, and
there often is relatively little energy involved. However, if line crews
encounter a transformer with arresters in ferroresonance, they should
always deenergize the unit and allow the arresters to cool. An overheated arrester could fail violently if suddenly reconnected to a source
with significant short-circuit capacity.
Ferroresonance occurs when the cable capacitance reaches a critical
value sufficient to resonate with the transformer inductance (see Fig.
4.11). Therefore, one strategy to minimize the risk of frequent ferroresonance problems is to limit the length of cable runs. This is difficult to do
for transformers with delta primary connections because with the high
magnetizing reactance of modern transformers, ferroresonance can
occur for cable runs of less than 100 ft. The grounded wye-wye connection will generally tolerate a few hundred feet of cable without exceeding
125 percent voltage during single-phasing situations. The allowable
length of cable is also dependent on the voltage level with the general
trend being that the higher the system voltage, the shorter the cable.
However, modern trends in transformer designs with lower losses and
exciting currents are making it more difficult to completely avoid ferroresonance at all primary distribution voltage levels.
The location of switching when energizing or deenergizing a transformer can play a critical role in reducing the likelihood of ferroresonance. Consider the two cable-transformer switching sequences in Fig.
4.39. Figure 4.39a depicts switching at the transformer terminals after
the underground cable is energized, i.e., switch L is closed first, followed by switch R. Ferroresonance is less likely to occur since the
equivalent capacitance seen from an open phase after each phase of
switch R closes is the transformer’s internal capacitance and does not
involve the cable capacitance. Figure 4.39b depicts energization of the
Transient Overvoltages 159
Transient Overvoltages
Downloaded from Digital Engineering Library @ McGraw-Hill (www.digitalengineeringlibrary.com)
Copyright © 2004 The McGraw-Hill Companies. All rights reserved.
Any use is subject to the Terms of Use as given at the website.
transformer remotely from another point in the cable system. The
equivalent capacitance seen from switch L is the cable capacitance, and
the likelihood of ferroresonance is much greater. Thus, one of the common rules to prevent ferroresonance during cable switching is to switch
the transformer by pulling the elbows at the primary terminals. There
is little internal capacitance, and the losses of the transformers are
usually sufficient to prevent resonance with this small capacitance.
This is still a good general rule, although the reader should be aware
that some modern transformers violate this rule. Low-loss transformers, particularly those built with an amorphous metal core, are prone
to ferroresonance with their internal capacitances.
4.7 Switching Transient Problems
with Loads
This section describes some transient problems related to loads and
load switching.
160 Chapter Four
(a)
underground cable
Switch L Switch R
(b)
underground cable
Switch L Switch R
Figure 4.39 Switching at the transformer terminals (a) reduces the risk of isolating the transformer on sufficient capacitance to cause ferroresonance as
opposed to (b) switching at some other location upline.
Transient Overvoltages
Downloaded from Digital Engineering Library @ McGraw-Hill (www.digitalengineeringlibrary.com)
Copyright © 2004 The McGraw-Hill Companies. All rights reserved.
Any use is subject to the Terms of Use as given at the website.
4.7.1 Nuisance tripping of ASDs
Most adjustable-speed drives typically use a voltage source inverter
(VSI) design with a capacitor in the dc link. The controls are sensitive
to dc overvoltages and may trip the drive at a level as low as 117 percent. Since transient voltages due to utility capacitor switching typically exceed 130 percent, the probability of nuisance tripping of the
drive is high. One set of typical waveforms for this phenomenon is
shown in Fig. 4.40.
The most effective way to eliminate nuisance tripping of small drives
is to isolate them from the power system with ac line chokes. The additional series inductance of the choke will reduce the transient voltage
magnitude that appears at the input to the adjustable-speed drive.
Determining the precise inductor size required for a particular application (based on utility capacitor size, transformer size, etc.) requires a
fairly detailed transient simulation. A series choke size of 3 percent
based on the drive kVA rating is usually sufficient.
4.7.2 Transients from load switching
Deenergizing inductive circuits with air-gap switches, such as relays
and contactors, can generate bursts of high-frequency impulses. Figure
4.41 shows an example. ANSI/IEEE C62.41-1991, Recommended
Practice for Surge Voltages in Low-Voltage AC Power Circuits, cites a
representative 15-ms burst composed of impulses having 5-ns rise
Transient Overvoltages 161
480-V Bus Voltage (phase-to-phase)
33.3 50.0 66.7 83.3 100.0 116.7
–1500
–1000
–500
0
500
1000
1500 Voltage (V)
Time (ms)
Figure 4.40 Effect of capacitor switching on adjustable-speed-drive ac current and dc
voltage.
Transient Overvoltages
Downloaded from Digital Engineering Library @ McGraw-Hill (www.digitalengineeringlibrary.com)
Copyright © 2004 The McGraw-Hill Companies. All rights reserved.
Any use is subject to the Terms of Use as given at the website.