CITY OF PRINEVILLE Prineville Airport
CROOK COUNTY Airport Layout Plan Report
fuel storage reserve should be identified in the terminal area(s) represented in the preferred
development alternative.
Airport Utilities
The existing utilities on the airport appear to be adequate for current and projected needs within
existing developed areas of the airport. Potential expansion of facilities on the north side of
Runway 10/28 would require extensions of the water, sewer, electrical, and telephone lines that
serve currently serve the east terminal area.
An increase in fire-related activity at airport may increase demand for water, although the
existing service should be able to provide adequate supply for the level of demand associated
with these operations. Overhead electrical and telephone lines should be buried whenever
possible; new electrical connections to hangars or other airfield developments should also be
placed underground. New airfield electrical requirements include providing power to the PAPIs
and REILs on the runway.
Security
The airport has limited wire fencing on portions of its boundary and chain link fencing around
some hangars. There are no major security concerns at the airport, although providing chain-link
fencing and gates along the entire landside frontage should be considered. Upgrading fencing
around the airport property line or to surround active areas of the airfield may be helpful in
reducing animal incursions.
The airport plans to develop hangars in the area located east of the current airport access road.
The general scheme involves developing a new access road east of the current location while
placing gates at each end of the current road. Since aircraft access would be provided through
this area (across the existing access road) the gates should remain closed and locked. Upgraded
security fencing will also be required in this area in conjunction with the new gates.
Additional flood lighting should be provided around the aircraft parking apron, fueling area, and
hangar areas to maintain adequate security.
FACILITY REQUIREMENTS SUMMARY
The projected twenty-year facility needs for Prineville Airport are summarized in Table 3-8. As
noted in the table, the primary facility requirements include runway and taxiway improvements
for Runway 10/28 and the addition of new hangar space on the airport. Maintaining and
July 2003 3-36 Facility Requirements
Century West Engineering Aron Faegre & Associates Gazeley & Associates