RISK MANAGEMENT
1. A project manager discovers that there is a part of the project that contains some risk. His strategy with this risk is to subcontract the work to
an outside supplier by using a firm fixed price contract. Which of the
following must the project manager do?
a. The project manager should make certain that the project team does
not reveal the risk to the supplier until the contract is signed.
b. The project manager should make every effort to make sure that the
supplier is made aware of the risk after the contract is signed.
c. The project manager should make sure that the supplier understands
the risk before the contract is signed.
d. The project manager should assign a member of the project team to
monitor the activity of the supplier to make sure that the supplier
deals with the risk properly if it occurs.
2. A project manager is faced with making a decision about a risk that the
team has identified. The risk involves the design of a bicycle. It has been
found that the neck of the bicycle, where the steering bearing is located
and the two supporting bars of the frame come together, will corrode
in a high salt environment. If this takes place the neck may fail and
injure the rider. The project team decides that the design of the bicycle
should be modified by using corrosion resistant materials in the design
of the neck. This will eliminate the risk from consideration. This technique is called:
a. Risk avoidance.
b. Risk acceptance.
c. Risk rejection.
d. Risk deflection.
3. A problem occurs in the design of a grocery cart. In this case it is
determined that the wheel will wear out much quicker in areas of heavy
snow and ice because the salt will corrode the wheel bearings. Using
sealed bearing wheels will significantly increase cost, and it is deter276