Thư viện tri thức trực tuyến
Kho tài liệu với 50,000+ tài liệu học thuật
© 2023 Siêu thị PDF - Kho tài liệu học thuật hàng đầu Việt Nam

MANAGING PROJECTS IN HUMAN RESOURCES, TRAINING AND DEVELOPMENT PHẦN 6 pps
Nội dung xem thử
Mô tả chi tiết
Table 8.2 Time estimates for relocation of an office
This example shows the time estimates for the activities identified in
Table 8.1.
Activities Estimated time in weeks
1. Prepare the site
1.1. Survey site
1.2. Plan alterations
1.3. Estimate building work
1.4. Contract builders
1.5. Purchase building materials
1.6. Carry out building work
1.1. About 3 weeks (needs
discussions and an expert)
1.2. Only 1 week once we have the
information
1.3. 1 week because we’ll need to call
builders in
1.4. 2 weeks because we need three
estimates and decision
1.5. 1 week because builders will
normally do most of this
1.6. About 4 weeks to knock down
walls and partition
2. Furnish and equip office
2.1. Plan furnishing needs
2.2. Identify what we have
2.3. Purchase furniture
2.4. Plan equipment needs
2.5. Identify what we have
2.6. Purchase equipment
2.7. Install equipment
2.8. Install furniture
2.1. 2 weeks because it needs
discussion with staff
2.2. 2 weeks – could be done in same
discussions
2.3. This normally takes 3 weeks to
deliver
2.4. 2 weeks – similar discussions
with staff needed
2.5. Same 2 weeks
2.6. Allow 3 weeks
2.7. 1 week
2.8. 1 week
3. Service preparation
3.1. Plan service during the move
3.2. Inform service users
3.3. Arrange resources needed
3.4. Deliver service during move
3.5. Prepare new staff locations and
rotas
3.6. Prepare info about new location
3.7. Inform when move completed
3.1. 2 weeks, needs discussion to
share space
3.2. 2 weeks, need to discuss who and
tell them
3.3. 2 weeks, might do this in same
discussions
3.4. 1 week duration of move
3.5. 4 weeks, could be tricky and a lot
to arrange
3.6. 3 weeks because we’ll need to
print new stationery
3.7. 1 week as this can all be done by
email and letter
102 Managing projects in human resources
As some of these activities had a lot of separate tasks, the project manager
checked each of these estimates against the task list to ensure that everything
had been considered.
Once the times have been estimated for each activity it is possible to draw
up a detailed schedule. You will probably have made a Gantt chart by this
time and you may like to revise it in the light of the information that is now
available. The revised Gantt chart may give enough information for you to
go ahead without any further scheduling if timing in the project is not a particular concern.
2.1 (any 2 weeks)
2.2 (any 2 weeks)
2.4 (any 2 weeks)
2.5 (any 2 weeks)
3.1 (any 2 weeks)
3.2 (any 2 weeks)
3.3 (any 2 weeks)
3.5 3.6
1.1
1 2 3 4 5 6 7 8 9 10 11 12 13 14
1.2 1.3 1.4 1.5 1.6
2.3 + 2.6 2.7
2.8
3.4 3.7
Figure 8.2 Critical path for relocation of an office
If the timescale is important there is a technique that can help you to be
much more precise about the timing of each element and the sequence in
which they need to be completed in order to complete the whole project in
the shortest possible time. This is called critical path analysis, and is sometimes referred to as CPA. The critical path is the shortest possible time in
which the project can be completed once the timing of each task and the necessary sequencing has been taken into account. The activities and their
timings can be drawn on a chart that shows the paths that each activity must
take and their relationships to each other. In particular, this chart shows the
dependencies. Dependencies are when one activity cannot start until another
is completed. It is usually the impact of dependencies that slows a project
down, and so the dependencies and the resulting sequence need to be identified to establish the critical path (see Figure 8.2).
Scheduling 103